{"id":1206,"date":"2026-11-10T03:20:00","date_gmt":"2026-11-10T03:20:00","guid":{"rendered":"https:\/\/bhaso.com\/blog\/?p=1206"},"modified":"2026-11-10T03:20:00","modified_gmt":"2026-11-10T03:20:00","slug":"launch-premortem-explained","status":"publish","type":"post","link":"https:\/\/bhaso.com\/blog\/launch-premortem-explained\/","title":{"rendered":"Pre-Mortem Explained: Imagine the Launch Failed, Then Ask Why"},"content":{"rendered":"<p>Most business projects begin with a confident slide. The launch date is set, the budget is approved, and everyone in the room can picture the announcement going out. What rarely appears on that slide is a candid list of the ways the launch could go wrong. A pre-mortem is a simple technique for producing that list. This explainer defines the term in plain language, shows how a small team can use it before releasing a new product or service, and points out where it tends to go astray.<\/p>\n<h2>What a pre-mortem means<\/h2>\n<p>You already know the post-mortem: after something fails, the team meets to work out why. A pre-mortem swaps the order. Before the work is finished, the team assumes it has failed and asks, &#8220;What was the most likely cause?&#8221; The imagined failure is the starting point, and the reasons are written as though they were already history.<\/p>\n<p>The reversal matters because of how people behave in planning meetings. Raising a concern can feel like criticising a colleague or doubting the plan. When the premise is that failure has already happened, concern becomes a contribution rather than an objection. People who stayed quiet in the planning stage often produce the most useful items.<\/p>\n<h2>Why a plan needs this exercise<\/h2>\n<p>Optimism is useful for starting things and unreliable for checking them. A team that has worked on a plan for weeks sees the steps that are present and overlooks the ones that are missing. The pre-mortem adds a deliberate pause to look for the missing steps while changing them is still inexpensive. A fix in the planning week might cost a conversation. The same fix after launch might cost customers.<\/p>\n<h2>A plain-language walk-through<\/h2>\n<p>Imagine a small company about to open a new online ordering service. The team is excited, and the plan covers the website, the payment page and the marketing email. A pre-mortem would proceed in four short steps.<\/p>\n<ol>\n<li><strong>State the failure.<\/strong> &#8220;It is three months after launch and the service has been quietly shelved.&#8221;<\/li>\n<li><strong>Write reasons alone.<\/strong> Each person spends five minutes writing every plausible cause on separate notes.<\/li>\n<li><strong>Read them aloud and group them.<\/strong> Similar notes sit together, and patterns appear.<\/li>\n<li><strong>Choose and assign.<\/strong> The team picks the few causes that are both likely and fixable, and gives each a named owner and a date.<\/li>\n<\/ol>\n<p>The notes from that ordering-service example might include: customers could not find the order button on a phone; the payment provider flagged early transactions for review; support staff were never told about the new service; and the one developer who understood the checkout was on holiday during launch week. None of these is a technical marvel. All are ordinary, and all are preventable.<\/p>\n<h2>The kinds of causes that keep showing up<\/h2>\n<p>Across different industries, the imagined failures fall into a handful of familiar families. It can help to keep the list in front of the team to prompt memory.<\/p>\n<ul>\n<li><strong>People and handoffs.<\/strong> Who is told what, and when? Gaps between teams are a frequent source of trouble.<\/li>\n<li><strong>Dependencies.<\/strong> Suppliers, payment services and approvals that you do not control.<\/li>\n<li><strong>Timing.<\/strong> Deadlines that leave no slack for testing or correction.<\/li>\n<li><strong>Money.<\/strong> Costs that grow while income arrives later than expected. A guide to <a href=\"https:\/\/bhaso.com\/blog\/mastering-modern-cash-flow-how-to-spot-spending-leaks-protect-digital-payments-and-extend-runway\/\">catching spending leaks and stretching runway<\/a> covers the financial side of this family in more depth.<\/li>\n<li><strong>Customer reality.<\/strong> The product works, but real users behave differently from the assumptions behind it.<\/li>\n<li><strong>Technology and security.<\/strong> The software that delivers the product and the pipeline that ships it both need attention.<\/li>\n<\/ul>\n<h2>Where technology risk enters the picture<\/h2>\n<p>For any team that ships software, one imagined failure deserves particular space on the wall: the release itself. Code travels through a build and delivery chain before it reaches users, and that chain can break or be misused. <a href=\"https:\/\/www.devsecopsnow.com\/\">DevSecOps Now<\/a> is a DevSecOps site whose blog is largely about securing CI\/CD pipelines, which makes it a handy reading list for teams wanting vocabulary for this part of the pre-mortem.<\/p>\n<p>You do not need to become a security specialist to benefit. Ask the plain question: &#8220;If the release failed, which step in our delivery chain would we suspect first, and who would notice?&#8221; The answer often reveals an unowned step.<\/p>\n<h2>Turning a business plan into a pre-mortem prompt<\/h2>\n<p>Teams that build a growth plan can use the same frame on each major bet. If your plan relies on bringing customers in through the product itself, then the assumptions underneath it are worth testing. A discussion of <a href=\"https:\/\/bhaso.com\/blog\/strategic-insights-for-product-led-growth-maximizing-success-with-bhaso-com\/\">building growth around the product experience<\/a> lays out the logic of that approach, and a pre-mortem is the natural companion: assume the bet did not pay off and ask which assumption was wrong.<\/p>\n<p>Similarly, when a company is choosing which digital tools to adopt, imagine that the adoption stalled. Perhaps nobody was trained, or the tool duplicated something already in use. A short <a href=\"https:\/\/bhaso.com\/blog\/navigating-business-technology-solutions-with-bhaso-com\/\">look at how businesses navigate technology solutions<\/a> gives context for the decisions that tend to deserve this treatment.<\/p>\n<h2>Common mistakes when running one<\/h2>\n<p>Facilitators stumble in three predictable ways. One is running the session after the decision is already final, so nothing found can change anything. Hold it while the plan can still bend. Another is letting the most senior person speak first, which narrows the list. Collect notes in writing before any discussion. The last is producing a long list and stopping there. A pre-mortem that does not end with owners and dates is only a worry exercise.<\/p>\n<h2>A quick template<\/h2>\n<p>If you want to try this tomorrow, use the following outline for a thirty-minute meeting:<\/p>\n<ul>\n<li>Five minutes: state the goal and the failure premise.<\/li>\n<li>Five minutes: silent writing of reasons.<\/li>\n<li>Ten minutes: read, group and discuss.<\/li>\n<li>Ten minutes: pick the top few, assign owners, set dates.<\/li>\n<\/ul>\n<p>Review the list at the next milestone to see which items were real, because the exercise improves with practice. After two or three rounds, teams usually find that their ordinary planning documents have started to include the risks they once only imagined.<\/p>\n<h2>The takeaway<\/h2>\n<p>A pre-mortem asks a team to pretend the project has failed and to explain, in specific terms, why. It costs an hour, it needs no special tools, and it surfaces issues when they are still easy to fix. Used honestly, it turns hopeful plans into tested ones. Next time a launch date goes on the calendar, add one more entry beside it: a short meeting where everyone is invited to imagine the worst and say what caused it.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>A plain-language explanation of the pre-mortem: assume your product launch has already failed, write down why, and fix the likely causes while it is still cheap.<\/p>\n","protected":false},"author":6,"featured_media":1207,"comment_status":"","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[166],"tags":[],"class_list":["post-1206","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-business-technology"],"_links":{"self":[{"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/posts\/1206","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/users\/6"}],"replies":[{"embeddable":true,"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/comments?post=1206"}],"version-history":[{"count":1,"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/posts\/1206\/revisions"}],"predecessor-version":[{"id":1263,"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/posts\/1206\/revisions\/1263"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/media\/1207"}],"wp:attachment":[{"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/media?parent=1206"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/categories?post=1206"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/bhaso.com\/blog\/wp-json\/wp\/v2\/tags?post=1206"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}